PURPOSES : The evaluation of the pavement condition of the asphalt concrete pavement of No. 2 runway of Inchon International Airport through PMS, a supporting system for making a decision of pavement, maintenance and repair, was made, and the proper time for repair according to the PCI reduction rate was suggested.
METHODS: By comparing and analyzing the evaluation results of pavements built in 2009, 2010, 2011, PCI change in each facility (No. 2 runway, C parallel taxiway, connection taxiway) was calculated. By applying the calculated change to PCI deduction rate model, the pavement condition of the target sections was estimated, and then the necessary section and time for repair were chosen.
RESULTS: After careful consideration of the time for pavement and maintenance, based on the result of PCI prediction, it was estimated that the southern takeoff and landing section of No. 2 runway was required to be repaired in 2012; connection taxiway in 2013; and C parallel taxiway in 2014; however, the section which is the main moving route of connection taxiway and C parallel taxiway was needed to be repaired in 2012.
CONCLUSIONS: For maintenance and repair of airport pavements, the optimal alternative should be chosen by considering economics and operability, via examining the time for repair and the aspect of management all together on the basis of this study.