A Methodology for Analyzing on the Correlation of Factors Affecting the Acquisition of Military Weapons Systems : Focused on Factor Analysis of Naval Ship Acquisition Delay Cases KCI 등재

국방무기체계 획득영향요인 상호관계 분석 : 함정획득지연 사례 및 요인 분석을 중심으로

  • 언어KOR
  • URLhttps://db.koreascholar.com/Article/Detail/404263
구독 기관 인증 시 무료 이용이 가능합니다. 4,200원
한국산업경영시스템학회지 (Journal of Society of Korea Industrial and Systems Engineering)
한국산업경영시스템학회 (Society of Korea Industrial and Systems Engineering)
초록

Naval weapons systems of the Republic of Korea are acquired through the Defense Planning Management System. Recently, acquisition of some naval ships have been delayed, and the causes of the delays have been recognized as inappropriate project management at the Execution Phase. However, we argue that the delay problem in naval ships acquisition should be approached, with due regard for the entire Defense Planning Management System. That is, We should try to investigate from Planning Phase to those of Programming, Budgeting and Execution Phases. Therefore, in this study, we investigated the actual cases of the delay in naval acquisition at all phases of the Defense Planning Management System. Based on the investigation, we tried to identify the naval ship Acquisition Delay Factors and find out the Weights of those factors. As the next step, we calculated the Influence Measures on the naval missions, including the Cost of Naval Capability Gap derived from the delays in acquisition of naval ships. As a final step, we calculated the Acquisition Delay Measures based on the interrelationship between the Acquisition Delay Factors and the Influence Measures. Then we evaluated and analyzed what the results stand for. Finally, we made suggestions for future improvement. The improvement suggestions we made for preventing delay in acquisition of naval ships in this study are as follows. First, we need a shift in perception. It is necessary to measure the Acquisition Delay Factors in acquiring naval ships and manage them from the Planning Phase. Second, resolution must be concerted efforts. All relevant agencies, not just a few, should work together to resolve the problems of acquisition delay. Third, analysis must be based on the accumulation of data. This allows the elaborating of naval ship Acquisition Delay Factors and Delay Measures. If this research method is applied to other military weapons systems in the future, we may be able to not just identify the Acquisition Delay Factors in acquisition of other military weapons systems, but also pursue improvement in those cases.

목차
1. 서 론
2. 함정무기체계 획득절차
3. 분석 절차 및 지연요인의 식별
    3.1 영향요인 상호관계 분석 절차 및 방법
    3.2 함정획득지연요인 식별 및 확정
4. 함정획득지연요인 상호관계 분석
    4.1 지연요인의 중요도 분석
    4.2 함정획득지연이 소요군에 미치는 영향력
    4.3 지연척도 산출
    4.4 결과 분석 및 개선 방향
5. 결 론
References
저자
  • Jeong-Oh Hwang(한남대학교 산업공학과) | 황정오
  • Hyun-Seung Oh(한남대학교 산업공학과) | 오현승
  • Bong-Wan Choi(한남대학교 산업공학과) | 최봉완
  • Dong-Soon Yim(한남대학교 산업공학과) | 임동순 Corresponding Author