PURPOSES : The Korea Expressway Corporation has been working on an early remodeling project for the Jungbu Expressway, to prepare techniques for the rehabilitation of the old CRCP. In this study, a literature review, field survey, and thickness design using MEPGD were conducted. This is to provide a procedure for the pre-treatment, or repair of the existing pavement in the JungBu Expressway.
METHODS : To evaluate the pavement condition of the JungBu Expressway, the existing PMS data were analyzed, and field surveys were conducted for each pavement condition. The SMA overlay thickness design was performed using the pavement thickness design program (MEPGD). In addition, the repair procedure was reviewed considering the characteristics of the old CRCP in Korea.
RESULTS : From the analysis of existing PMS, field surveys, and laboratory tests, it was discovered that the old CRCP condition of the Jungbu Expressway was not satisfactory. Using MEPDG, the SMA thicknesses for each scenario were proposed as 5, 8, and 10 cm. In addition, appropriate repair procedures for each distress type(punchpout, multiple repair, re-failure, failure of longitudinal joint, etc.) of damaged CRCP in Korea were proposed.
CONCLUSIONS : For the remodeling project of the Jungbu Expressway, appropriate repairs should be performed for each type of distress in the old CRCP. In this study, an appropriate overlay thickness and pre-treatment method are suggested.