1. Introduction 2. Scope and review of constructability 2.1 Constructability range 2.2 Constructability review 3. Constructability review for NSSSequipment of new NPP project 3.1 Purpose and Key feature 3.2 NSSS equipment installation plan review ofthe New nuclear power plant (Installationin using Open Top Method) 3.3 NSSS equipment dismantling plan reviewof the New nuclear power plant (Takingout in using the Side Method) 4. Conclusion
저자
Jun Hee Lee(KEPCO E&C, 269 Hyeoksin-ro, Gimcheon-si, Gyeongsangbuk-do, Korea)