Construction period is one of the most important factors which influence on cost and quality in nuclear power plant construction. As part of continued efforts for the competent reactor type, the construction improvements such as application of mechanical rebar splice, optimum lift height for concrete placement and enlargement of liner plate module in the reactor building wall are developed to minimize the construction period. This study referred to knowledge and experiences from APR+(Advanced Power Reactor Plus) technical development. The proposed method can be applied to the APR+ in the near future.