Kori unit 1 was permanently shut down in 2007 and is currently awaiting approval for decommissioning and dismantling (D&D). The wastes generated during decommissioning is estimated to be approximately 14,500 of 200 L drums. In this study, the treatment process of decommissioning wastes will be reviewed through the case of the US Zion nuclear power station (ZNPS). Zion unit 1 and 2 received an operating license in 1973 and were permanently shut down and the spent nuclear fuel was transferred to the pool in 1998. The decommissioning was carried out according to the following five steps; (1) safe storage (SAFSTOR) dormancy, (2) preparation for decommissioning, (3) establishment of independent spent fuel storage installation (ISFSI) and transfer of the spent fuel and greater than class C radioactive materials, (4) decommissioning operations and (5) site restoration. The total volume of waste generated during decommissioning was expected to be approximately 1.7×105 m3. This is far above the Kori unit 1 waste estimation because ZNPS has a history of accidents and includes soil waste. Wastes were treated differently according to their properties and locations.