        1.
        2023.11 구독 인증기관·개인회원 무료
        Wolsong Unit 1, a domestic heavy water reactor nuclear power plant, was permanently shut down in December 2019. Accordingly, Wolsong Unit 1 plans to prepare a Final Decommissioning Plan (FDP), submit it to the government by 2024, receive approval for decommissioning, and begin full-scale decommissioning. One of the important tasks in the decommissioning of Wolsong Unit 1 is to determine the decommissioning strategy. It is necessary to decide on a decommissioning strategy considering various factors and variables, secure the technical background, and justify it. The selection of a decommissioning strategy is best achieved through the use of formal decisionmaking assistance techniques, such as considerations related to influencing factors. It is very important to understand the basic decommissioning strategy alternatives and whether sufficient consideration has been given to situations where only a single unit is permanently shut down in a multi-unit site like Wolsong Unit 1, while the remaining units are in normal operation. As a process for selecting a decommissioning strategy, first, all considerations that could potentially affect decommissioning presented in the KINS Decommissioning Safety Review Guidelines were synthesized, influencing factors to be used in the decision-making process were determined, and the concept was defined. In order to select the most appropriate decommissioning strategy by considering various evaluation attributes of possible decommissioning alternatives (immediate dismantling and delayed dismantling), the Wolsong Unit 1 decommissioning strategy was evaluated by reflecting the AHP decision-making technique.
        2.
        2023.05 구독 인증기관·개인회원 무료
        As an initial part of Kori-1 & Wolsung-1 Unit decommissioning planning, a characterization plan is developed to define the nature, extent and location of contaminants, determine sampling locations and protocols, determine quality assurance objectives for characterization, and define documentation requirements. The actual characterization of a facility is an iterative process that involves initial sampling according to the characterization plan, field management (such as labeling, packaging, storing, and transport) of the samples, laboratory analysis, conformance to the data quality objectives (DQOs), and then identifying any additional sampling required, refining the DQOs, and modifying the characterization plan accordingly. The final product of the facility characterization is a document that describes the type, amount, and location of contaminants that will require consideration and removal during the decommissioning operations sufficient to prepare a decommissioning plan. In this study, implementing a characterization plan, developed in accordance with this standard, will result in obtaining or deriving the above information.
        3.
        2023.05 구독 인증기관·개인회원 무료
        Kori Nuclear Power Plant Unit 1, which began operating in 1978, is Korea’s oldest commercial nuclear reactor. The reactor was permanently shut down in June 2017, and now the decommissioning process has begun. The decommissioning process will generate a significant amount of waste that requires appropriate management to minimize the impact on the environment and human health. And the waste routing, i.e. the activities and logistics for managing the material generated, is a key point in a decommissioning project. It determines the routes from the material inventory to the envisaged material end states. In this study, we review on several factors for the selection of the waste routes in a decommissioning project. In terms of sustainability, the ‘waste hierarchy’ should be applied to routing materials from nuclear facilities. According to the waste hierarchy, the preferred end state is reuse or recycling of the waste as material or, more preferably, the avoidance of waste generation. In addition, treatments (such as decontamination and thermal treatment) that can reduce the volumes requiring disposal as radioactive waste should be considered. Another important parameter is the need to secure availability and capacity of waste routes. Short-term bottlenecks or any delay in the removal of the waste from the site often has an impact on other site activities. If possible, at least two alternative waste routes should be identified for the main categories of waste and kept available throughout the decommissioning project. All routes should be direct to the material end state if possible, but it is more important that waste is removed from the site so that other site operations are not impeded.
        4.
        2008.06 구독 인증기관 무료, 개인회원 유료
        The objective of this study was to determine the potential hazardous effects of sorting process by flowcytometry on the quality of boar spermatozoa by flowcytometer. Freshly collected boar semen was diluted and divided into two groups; control none sorted and sorted. Sperms in sorted group were processed with flowcytometer for cell sorting with 100 uM nozzle under the 20 psi pressure. Measurements on each parameter were made at two time points, 0hr (right after sorting) and 24 hr post sorting. Although there was a tendency of lower viability in sorted group than none sorted control group, the percentage of live cells in control(75.83+-6.92 & 59.53+-10.34) was not significantly different from sorted (59.7+-7.34 & 43.97+-3.76) at both 0 and 24 hr post sorting. However, sorted sperm showed significantly lower mitochondrial function compared to the control at both 0 h (79.37+-3.22 vs. 63.50+-10.05) and 24hr(67.27+-3.22 vs. 46.97+-5.37) time points (p<0.007). Sperm DNA fragmentation rate was significantly lower in control (22.0+-7.04) than that of sorted (32.27+-7.49) at 24 hr time point (p<0.0002). Taken together, these data suggested thatsorting process by flowcytometer may have influenced sperm motility rather than viability. Also high speed sperm sorting by flowcytometer has significant effects on DNA fragmentation on elapsed time after sorting.
        3,000원
        5.
        2014.03 KCI 등재 서비스 종료(열람 제한)
        Early growth response 1 (Egr1) is a zinc-finger transcription factor to direct second-wave gene expression leading to cell growth, differentiation and/or apoptosis. While it is well-known that Egr1 controls transcription of an array of targets in various cell types, downstream target gene(s) whose transcription is regulated by Egr1 in the uterus has not been identified yet. Thus, we have tried to identify a list of potential target genes of Egr1 in the uterus by performing multi-step in silico promoter analyses. Analyses of mRNA microarray data provided a cohort of genes (102 genes) which were differentially expressed (DEGs) in the uterus between Egr1(+/+) and Egr1(–/–) mice. In mice, the frequency of putative EGR1 binding sites (EBS) in the promoter of DEGs is significantly higher than that of randomly selected non-DEGs, although it is not correlated with expression levels of DEGs. Furthermore, EBS are considerably enriched within –500 bp of DEG’s promoters. Comparative analyses for EBS of DEGs with the promoters of other species provided power to distinguish DEGs with higher probability as EGR1 direct target genes. Eleven EBS in the promoters of 9 genes among analyzed DEGs are conserved between various species including human. In conclusion, this study provides evidence that analyses of mRNA expression profiles followed by two-step in silico analyses could provide a list of putative Egr1 direct target genes in the uterus where any known direct target genes are yet reported for further functional studies.